I have ~~two~~ three stories.
Company X: Our testbed server room was supported by redundant rooftop AC units, many yards apart. During a storm, a lightning bolt forked (split) One tip.of the bolt hit AC unit one and the other hit AC unit two, killing both cooling units. To make things worse, the server manufacturer did not add a temperature safety shutdown to the units and instead configured them to fan faster the hotter they got. By the time I got there the cable management was warping and melting due to heat.
Company Y: The main datacenter was on tower 2 and the backup datacenter was on tower 1. Most IT staff was present when the planes hit.
EDIT:
Company Z: I started work at a company where they gave me access to a "test" BigIP (unit 3) to use as my own little playground. Prior to my joining the company was run by devs doubling as IT. I deleted the old spaghetti code rules so that I could start from scratch. So, after verifying that no automation was running on my unit (unit 3), I deleted the old rules. Unfortunately the devs/admins forgot to disengage replication on "unit 2" when they gave me "unit 3". So production "unit 2" deleted its rules and told production "unit 1" to do the same. Poof...production down and units offline. I had to drive four hours to the datacenter and code the entire BigIP from scratch and under duress. I quit that job months after starting. Some shops are run so poorly that they end up fostering a toxic environment.