this post was submitted on 17 Mar 2024
81 points (96.6% liked)

Asklemmy

43818 readers
880 users here now

A loosely moderated place to ask open-ended questions

Search asklemmy ๐Ÿ”

If your post meets the following criteria, it's welcome here!

  1. Open-ended question
  2. Not offensive: at this point, we do not have the bandwidth to moderate overtly political discussions. Assume best intent and be excellent to each other.
  3. Not regarding using or support for Lemmy: context, see the list of support communities and tools for finding communities below
  4. Not ad nauseam inducing: please make sure it is a question that would be new to most members
  5. An actual topic of discussion

Looking for support?

Looking for a community?

~Icon~ ~by~ ~@Double_[email protected]~

founded 5 years ago
MODERATORS
you are viewing a single comment's thread
view the rest of the comments
[โ€“] [email protected] 35 points 7 months ago (1 children)

They had a multimillion dollar transit project near where I loved, like $112 million to replace a train station, a subway stop, and a major bus terminal to combine them into a single entity near Washington DC. They projected 3 years from start to finish, but it took almost 7. They had to reroute the entire bus terminal to surrounding streets and parking garages, which was a traffic nightmare. People using the train station or subway had to reroute their walk sometimes up to a mile off their present walk. While doing demolition, they found that the previous bus terminal was on the site of an old gas station which had been improperly sealed off: they just filled the tanks with concrete. Underneath that, they found tons of the the natural mineral serpentine, which naturally contains asbestos. So now they had a biological hazard which they had spent the last few months blowing up with dynamite into the surrounding city. After that was cleaned up and sealed, The got underway.

There were a ton of other mistakes, but when it was completed, they found defects. The superstructure is made of concrete and thus construction specifications were replete with engineering criteria for the composition of the concrete, and its pouring, curing and tensioning. The Inspector General systematically examined 22 project management and control points from the time concrete was mixed until the time it was ready for final inspection. 14 of 22 control points that should have minimized defects were weak or ineffective. Those defects may require recurring engineering inspections, higher maintenance costs, and they could shorten the planned 50-year useful life. In addition, the IG described the risk of concrete falling onto transit-center patrons.

The entire thing was a huge boondoggle costing the downtown untold millions into the future.

[โ€“] [email protected] 2 points 7 months ago (2 children)

Iโ€™m curious: Which station was this?

[โ€“] [email protected] 5 points 7 months ago

Not sure which station they're talking about but I know the silver line was plagued with concrete issues.