this post was submitted on 08 Jul 2024
13 points (93.3% liked)
Aotearoa / New Zealand
1648 readers
14 users here now
Kia ora and welcome to !newzealand, a place to share and discuss anything about Aotearoa in general
- For politics , please use [email protected]
- Shitposts, circlejerks, memes, and non-NZ topics belong in [email protected]
- If you need help using Lemmy.nz, go to [email protected]
- NZ regional and special interest communities
Rules:
FAQ ~ NZ Community List ~ Join Matrix chatroom
Banner image by Bernard Spragg
Got an idea for next month's banner?
founded 1 year ago
MODERATORS
you are viewing a single comment's thread
view the rest of the comments
view the rest of the comments
This is how power line deicing works on systems overseas. You need two legs to the circuit, so it would involve either isolating lines from each other on double track, or earthing out the end of the lines, and using the tracks as a return path.
The option I was actually thinking about was having a heated pantograph of some type.
https://en.m.wikipedia.org/wiki/Levis_De-Icer
That's really cool! It sounds like they switch the section to a separate circuit and then pile a carefully controlled high voltage current into it to warm up the line without melting it. But it also says the line remains operational, if I'm reading it right. Not sure how you send too much power through the line without affecting the trains using the line.
Anyway, it sounds like this is the only system like it in the world, and it was installed after heavy snow caused a collapse of much of the network. What I take from that is that it's probably really expensive to install, and probably not worth it in Wellington. One of the ice scraping pantograph options probably makes more sense.
I guess for your heated pantograph option you'd run it on a special de-icer train at low speed? I would think melting the ice off via a pantograph would take a really long time.
The line is out of action while deicing is taking place, but only for the shortest amount of time necessary.
That's what I'm thinking, yes. Although you could pump a lot of heat into the pantograph, and pair it up with a scraper at the same time.
It wouldn't be able to run line speed, but it would be reasonably fast, I'd think.
Ah yes paired with a scaper that would be quite effective. I was thinking you melt it but then the heat is gone and the cable is still frozen so it would refreeze. But if you soften it with the heat then scape it, that could work quite well.
Probably not much chance of getting it implemented in Wellington, though. There might be a slim chance if there was an off the shelf solution, but from my reading into this is seems everything is quite custom.